How to maintain the OH800-OH1000 oxyhydrogen generator ?

OH 800-1000 Oxy-hydrogen Generator


Maintenance Guide


• Electrolytic cell maintenance

1. Electrolytic cell cleaning

The OH800-1000 electrolytic cell adopts the bellows heat dissipation principle. It is small in size and easy to maintain. The user should follow this guide to perform maintenance on the electrolytic cell after 500 hours of use. If it is less than 500 hours, maintenance should be performed within 1 year.

The method is as follows:


A. Turn off the power switch of the equipment, unplug the plug or disconnect the power cord from the external circuit breaker.

B. Open the vent valve to release the remaining gas inside the equipment (reset the pressure gauge to zero), use a 17mm open-end wrench to open the electrolytic cell liquid replacement cover (water addition cover).

C. Facing the equipment operation panel, open the door on the right side of the equipment. There is a drain valve on the heat dissipation axial flow fan at the bottom of the electrolytic cell. Open it.

D. Add pressurized clean water from the water inlet to flush the inside of the electrolytic cell until clean water flows out of the drain valve. During the flushing process, you can shake the machine appropriately to allow the dirty liquid to flow out quickly.


2. Electrolyte ratio

A. The main component of the electrolyte used in this equipment is potassium hydroxide (industrial KOH, purity is more than 90%) mixed with pure water (distilled water is best, tap water is prohibited)

B. The blending ratio is a weight ratio of 1:3, 1KG potassium hydroxide (KOH) is mixed with 3KG pure water.

Note: The device will be given a hydrometer when it leaves the factory, which the user can use when mixing. The concentration ratio is 25% - 30%.

C. Steps:

Because KOH is highly alkaline and corrosive, it will generate high temperature when dissolved in water, so before mixing, we should prepare a high temperature resistant container (the material requirements are generally stainless steel, high temperature resistant glass, porcelain, etc.), and wear protective equipment (such as protective gloves, masks, etc.)


1) Pour the prepared pure water into the container

2) Add corresponding KOH

3) Use a stirring rod to stir evenly and wait for the electrolyte to cool to room temperature

4) Add electrolyte into the electrolytic cell

The electrolyte capacity of the model is as follows:

Model OH800 OH1000
Electrolytic cell capacity 11KG 15KG

3. Add liquid to the electrolytic cell

A. Close the drain valve, power on the equipment, the operation screen will prompt that the electrolytic cell is short of liquid and the alarm will ring

B. Slowly add electrolyte from the filling port until the alarm stops ringing

C. Tighten the filling cap


• Filter maintenance

Check the filter element before use and replace it in time if it is damaged.

Rinse the filter cup with clean water every week. Method: Open the filter cup filling port, open the filter cup discharge port, add clean water from the filling port and rinse until the liquid out is clear water; close the valve and filling port after cleaning.


• Cleaning and maintenance of circuit components

The circuit components in the equipment mainly include electrolytic power supply, control system, and axial flow cooling fan. Users should check the above parts regularly (monthly or weekly) when using the equipment. After using the equipment for a period of time, dust will inevitably accumulate. If it is not cleaned for a long time, it will affect the heat dissipation of components and even cause equipment failure. Therefore, users should regularly (monthly) use compressed air to blow and clean the dust covered on the circuit components of the equipment.


• Other maintenance refers to the cleaning and inspection of the internal structure of the equipment. Users can clean the internal structure of the equipment regularly (monthly) in daily use, such as whether the cleaning is completed after the liquid is filled and overflowed, etc.


• Leak detection

In the process of using hydrogen and oxygen, leakage detection of gas accessories and equipment is a concern. Gas accessories and equipment should be tested every week. The specific methods are as follows:

1. Turn off the gas accessories (such as welding gun, close the gun outlet valve), and the equipment starts to produce gas.

2. Observe whether the pressure gauge pointer rises and whether its value is normal (the hydrogen-oxygen machine will automatically stop producing gas when the pressure is 0.2MPA/0.3MPA, and its error is 0.02MPA)

3. When the equipment operation interface prompts pressure protection and the pressure value is normal, turn off the main power of the hydrogen generator to stop gas production and record the pressure value

4. Let it stand for more than half an hour. If the pressure value does not change, there is no leakage. If it drops, check the leak point. Method: Cover each interface with soapy water to see if there are bubbles. If there are, it is a leak.

5. When discharging the remaining gas from the equipment, open the switch of the gas accessories (such as the gun valve), block the gas outlet (fire nozzle) with your hand, and immerse the gas accessories in water to check whether there is any leakage.


Okay Energy Equipment Co.,Ltd

Oxyhydrogen Generator Complete Safety Operation Guide
next
recommended for you
Get in touch with us
Offering CE/FCC/ISO-certified solutions with proven global case studies and an open invitation for worldwide distributors.
Contact Us
Contact Person: Sherry
Tel: +86-18932451962
WhatsApp: +86-18932451962
Company Address: No. 204, Building 2, Xinggong International Ind. Park, No. 100, Luyun Road, National High-Tech Development Zone, Yuelu District, Changsha, Hunan
Copyright © 2026 Okay Energy | Privacy Policy  |  | sitemap

Contact us
whatsapp
email
Contact customer service
Contact us
whatsapp
email
cancel
Customer service